Lights are up, steel work and new floor is in place.
Lift table will be centered under the trolley rail and the new furnace will hang in the right corner over the workbench.
Have a few outlets to run yet on the left wall as well as plumb the air line back in.
Will probably hang an air reel under the center of the work bench and run a line down the left wall as well then over the door to the mill
The mill will set in the corner where it is now, have yet to get the head back on and wired.
|